2017 Road Improvements

StreetLimit of WorkStatus
Archbold Place
Resurface Entire Length
Complete
Arlington AvenueResurface Entire Length
Complete
Boulevard (Between Park and Washington)
Resurface Boulevard (Between Park and Washington) Is a Carryover State and County Aid Project from 2016
Complete
Boulevard (Between Washington and Grove)
Resurface Boulevard (Between Washington and Grove) State Aid Project from 2017
Complete
Boulevard (Section of 800 Block from Grove)
Resurface Boulevard (Section of 800 Block from Grove)
Complete
Byron Court
Resurface Entire Length with Drainage
Complete
Caufield Drive (Fontana)Resurface Entire Length
Complete
Central Avenue
County Project: Resurface S Avenue to Town Line
Complete
Cory Place
Resurface Entire Length
Complete
Cranford Avenue
Resurface Benson to Sherman
Complete
Edgewood Avenue
Construct New Curbs and Resurface (Hanford to Clark)
Carried to 2018
Effingham Place
Resurface Entire Length
Complete
First Street
Construct New Curbs and Resurface (Scotch Plains to Florence) with Drainage
Carried to 2018
Grandview Avenue
Elizabeth
Complete
Harrison AvenueResurface Kimball to Raymond
Complete
Linden Avenue
Resurface Saunders to E Broad
Complete
Manchester Drive
Resurface Entire Loop
Complete
Oak Avenue
Resurface Entire Length
Complete
Parkview Avenue
Resurface Entire Length
Complete
Pine Grove Avenue
Resurface Entire Length
Complete
Ramapo WayResurface Entire Length with Drainage
Complete
Raymond Street
Resurface Entire Length
Complete
Reese Place
Resurface Entire Length
Complete
Roger Avenue
Resurface Entire Length
Complete
Shackamaxon Drive
Resurface Scotch Plains to Knollwood
Complete
Shadowlawn Drive
Resurface Scotch Plains to Rahway
Complete
Sherbrook Drive
Resurface Entire Length
Complete
Sherman Drive
Resurface Harding to St. MarksComplete
Stanley Avenue
Resurface E Broad to Lenox
Complete
Summit Court
Resurface Summit Avenue to Summit Court (Back End)
Complete